OperationsCosting an aggregate plan

Formulas for this chapter

Inventory rows

Beginning(t) = Ending(t-1) Ending(t) = Beginning(t) + Output(t) - Forecast(t) Average(t) = ( Beginning(t) + Ending(t) ) / 2

Every aggregate plan. If Ending would be negative, set it to zero and put the shortfall in the backlog row.

Output
Regular time plus part time plus overtime plus subcontract
Average
The row the carrying charge is applied to

Total cost of an aggregate plan

Total = Regular units x regular rate + Overtime units x overtime rate + Part-time units x part-time rate + Subcontract units x subcontract rate + Hire/layoff cost + Total AVERAGE inventory x carrying rate + Backlog units x backorder rate

Costing any plan. Give a per-period total row as well, so an error can be localised.

carrying rate
Cost per unit per period, applied to average inventory
backorder rate
Cost per unit per period of unmet demand; usually much higher than the carrying rate

Production-days output

Monthly output = output per day x production days in the month Level daily rate = total demand / total production days

When the problem gives working days per month. A constant daily rate gives an uneven monthly output.

output per day
Units the workforce produces in one working day
production days
Working days in that particular month
Step 2 of 19
The real wordsTheory

The rows, in order

Copy this skeleton onto your answer sheet before touching a number.

Forecast Output: Regular time / Part time / Overtime / Subcontract Output - Forecast Inventory: Beginning / Ending / Average Backlog -------------------------------------------------- Costs: Regular / Part time / Overtime / Subcontract Hire and layoff Inventory (on AVERAGE inventory) Back orders Total

The horizontal line matters. Everything above it is in units; everything below it is in money.