The real wordsTheory
The three averages
Average flow time = SUM of flow times / n
Average tardiness = SUM of days late / n
Average number of jobs at the work centre
= SUM of flow times / SUM of processing times
The third is the odd one out and is easy to forget. It measures work-in-process: jobs sitting in the shop are inventory, so a rule that lowers average flow time also lowers WIP.
The denominator of the third measure is the total processing time, which never changes with the sequence. So minimising total flow time and minimising average jobs in the shop are the same objective.